(not quite up to date, but probably still applicable) Construction Update as of September 19, 2006

The grinding of the asphalt surface between SW Edmunds Street and SW Genesee Street has been completed! The contractor is now working diligently to repair the concrete roadway base beneath the asphalt pavement. However, it has become evident that a greater level of repair is required than previously anticipated. The center lanes between SW Edmunds and SW Alaska Streets will remain closed until asphalt can be placed over the concrete to level the roadway base. This work is necessary before final asphalt paving of the roadway surface takes place. SDOT and the contractor are working to schedule this work, which is weather dependent, as soon as possible. We recognize the inconvenience and are committed to completing this work as quickly as possible. Thank you for your patience!

Upcoming work - September 18 - 22

Continued repairs to the concrete roadway base in spot locations.

Removal and replacement of concrete curb ramps at various locations.

The re-paving of the roadway with a new asphalt surface is expected to occur within the next three (3) to five (5) weeks.

Throughout the duration of the construction project, one lane of travel will be maintained in each direction during the hours of 4:00 PM to 6:00 PM. At other times, traffic may be restricted to one lane with the use of flaggers. Normal work hours for the contractor will be 7:00 AM to 4:00 PM.

For further information, please contact Jessica Murphy, P.E., Project Manager 684-0178 This email address is being protected from spambots. You need JavaScript enabled to view it.

Calendar

April 2019
S M T W T F S
31 1 2 3 4 5 6
7 8 9 10 11 12 13
14 15 16 17 18 19 20
21 22 23 24 25 26 27
28 29 30 1 2 3 4

Latest Events

No events

Login Form

If you would like to be included on the mail list send a request to: mocacnc@gmail.com